19.2MW Confidential Data Centre, Italy

Project Name

19.2MW Confidential Data Centre, Italy

Client:

Confidential Client

Project:

19.2MW Confidential Data Centre

Location:

Italy

Sectors:

Data Centres

Services:

Electrical Services and Instrumentation, Mechanical Piping & HVAC Services, and Off-Site Manufacturing

PROJECT DESCRIPTION

Kirby was appointed as GC2 to deliver the mechanical and electrical installations, associated GC2 works, commissioning management, and end-user fit-out works for a 19.2MW data centre in Milan, Italy.

Kirby also delivered the CAT B customer fit-out of the offices and data hall storage rooms

 

SCOPE OF WORK

Kirby scope of works included the mechanical, electrical and GC2 services. It also included management of commissioning across Levels 1 to 3 and support for Levels 4 and 5.

The electrical systems installed by Kirby included:

  • MV Distribution
  • LV Distribution
  • Generator
  • UPS
  • General & Emergency Lighting
  • General Service Power
  • Mechanical Plant Service Power
  • Fire Detection & Alarm
  • Access Control, Intruder & CCTV
  • Earthing & Bonding
  • Voice & Data Distribution
  • Lightning Protection
  • EMS
  • Scada
  • Busbar Balancing

The mechanical systems installed by Kirby included:

  • Chilled Water
  • Smoke & Heat Exhaust Ventilation
  • Supply & Extract Ventilation Distribution
  • Fire Suppression
  • VRF Air Conditioning
  • Leak Detection
  • BMS
  • Server Room Air Conditioning
  • Rain Water Harvesting
  • Low Temperature Hot Water
  • Process Waste
  • Soils & Wastes
  • Domestic Water Services
  • Heat Tracing
  • Condensate Drainage
  • Fuel System
  • Off-site modularisation of pipework, plant rooms and equipment

The GC2 scope of works completed by Kirby included:

  • Whitewall
  • Ceilings
  • Fire Stopping
  • Glazing
  • Handrails
  • Doors
  • Secondary Steel
  • Plinths and CSA Finishes
  • Bollards
  • CAT Ladders and Access Equipment

The commissioning scope of works completed by Kirby included:

  • Management of OFCI and CFCI vendors.
  • Development and implementation of load bank plans, including procurement, set-up, and balancing.
  • Mechanical system flow and pressure balancing, flushing, and chlorination.
  • Full control of hazardous energies on site using Authorised Person Office throughout energisation and commissioning stages.
  • Development and integration of commissioning schedules and plans.
  • Full provision of as-built and handover documentation including drawings, Sequences of Operation, Operating, Maintenance and Emergency procedures.
  • Completed commissioning of over 1,541 assets over several phases.

Delivered installation and turnover of various CFCI and OFCI equipment including: DBs, Vesda Panels, AHUs, 18 nr. Chillers, 9 nr. Buffer Vessels, 9 nr. Sprinkler Pump Sets, 12 nr. MV Generators, 2 nr. SUDB, 12 nr. MVTBS & GRMUs, MDSBs, MSBs, STSSBs, UPSs, UDPs, VFDs, STSs, 8 nr. Power Strings, 3 nr. Mechanical Power Strings and 1 nr. Redundancy Power Block, CRAHs, 24 nr. Diesel Bulk Tanks with associated control systems, 4 nr. AHUs, various VRF systems, various Fans, and DX systems, Cool Wall Sets for 8 nr. Data Halls and associated electrical rooms.

The total project meterage consisted of 86km of cable, 27.5km of containment, 1,000 instruments, 5.8km of pipework and 1,700m2 of ductwork.