Pernod Ricard, Ireland

Project Name

Pernod Ricard, Ireland

Client:

Irish Distillers

Main Contractor:

PM Group

Consultant:

PM Group

Project:

Garden and Columns Stillhouse

Location:

Cork, Ireland

Value:

€5.5m

Sectors:

Industrial

Services:

Electrical Services and Instrumentation and Off-Site Manufacturing

PROJECT DESCRIPTION

Pernod Ricard undertook a €100m investment at its plant in Midleton, Co. Cork in order to increase production capacity. The investment included the building of a new brewhouse, column stillhouse and distillation columns building.

On this project, Kirby installed the electrical and instrumentation services within the stillhouse and distillation columns building. This involved all main power distribution, motive power, instrumentation, lighting, general services and ancillary systems associated with equipment such as pot stills, condensers, separators, columns, vessels and tanks. Other equipment included ancillary plant such as pumps, heat exchangers and variable speed drives in both buildings and the external tank farms.

All work was undertaken within ATEX/Hazardous Area classifed zones with particular emphasis being placed on the quality of installed services including glanding and terminations. Work was delivered within an operational production facility. Through careful planning, off-site fabrication and the close working relationship between all project stakeholders, the investment was completed on schedule and within budget allocated.

SCOPE OF WORK

Kirby scope of works included the installation and commissioning of electrical and instrumentation services.

The electrical and instrumentation systems installed by Kirby included:

• MV Distribution
• LV Distribution
• UPS
• General & Emergency Lighting
• General Service Power
• Mechanical Plant Service Power
• Fire Detection & Alarm
• Access Control, Intruder & CCTV
• Earthing & Bonding
• Voice & Data Distribution
• Lightning Protection
• EMS
• Impulse Tubing
• SCS
• Profibus
• Scada

The total project meterage consisted of 90,000m of cable, 2,500m of containment, 100m of impulse piping, 1,500 number of instruments, 1,200 number of loops, 300 number of calibrations and 2,000 number of I/O points.